FIDIC claim time-bar calculator and a Notice of Claim template.

Enter the date you became aware of the event and see the last day for your Notice of Claim, your fully detailed claim and, for a continuing event, your final claim, under the 1999 or 2017 Red, Yellow and Silver Books. Add the dates to your calendar and download a Notice of Claim template in Word.

  • 1999 and 2017 editions
  • Periods you can change for your Particular Conditions
  • Notice of Claim template in English and Arabic

Claim calculator

Work out your claim deadlines

Choose the edition and the date you became aware of the event. The deadlines and the days left update as you type.

Particular Conditions often change them. Leave a field empty to use the period in the edition.

FIDIC counts calendar days, so weekends and public holidays count. The day you became aware is day 0. If a last day falls when your office or the Engineer’s is closed, send it earlier.

Your deadlines

  1. 1. Sub-Clause 20.2.1

    Notice of Claim

    Last day

    Sun 29 Nov 2026

    Give the Engineer a Notice of Claim as soon as practicable, and no later than this date, describing the event or circumstance. Mark it as a Notice and refer to the Sub-Clause (Sub-Clause 1.3). If you miss it, you lose the entitlement, and the other Party is discharged from liability for the event.

  2. 2. Sub-Clause 20.2.2

    Engineer’s initial response

    No fixed date

    If the Engineer considers the Notice of Claim late, it must say so within 14 days after receiving it. If it doesn’t, the Notice is deemed valid.

  3. 3. Sub-Clause 20.2.4

    Fully detailed Claim

    Last day

    Sun 24 Jan 2027

    Include a description of the event, a statement of the contractual and/or other legal basis, the contemporary records you rely on, and the amount and/or extension of time claimed, unless the Engineer agrees another period. If the statement of the legal basis is missing by this date, the Notice of Claim lapses, unless the Engineer fails to say so within 14 days.

  4. 4. Sub-Clauses 20.2.5 and 3.7

    Agreement or determination

    No fixed date

    The Engineer then agrees or determines the claim under Sub-Clause 3.7, within the time limits that Sub-Clause sets.

Download the Notice of Claim template (Word)

A guide to the general conditions, not legal advice. Check your Particular Conditions, and take legal advice on any claim you think may be late.

Runs in your browser. Nothing you type is sent to us or stored.

Authorized vendor to

  • Ministry of Finance
  • Ministry of Interior
  • DGE Abu Dhabi
  • Etihad Aviation
  • EDGE Group

Delivered for

  • Hindustan Unilever
  • Nokia
  • Linde
  • USA Today
  • JSL

Procurement-ready

  • Emirati national company
  • National ICV certificate
  • Abu Dhabi Government Procurement Gate
  • UAE Ministry of Finance, federal procurement
  • Registered ADNOC vendor

The 2017 procedure

How a claim runs under FIDIC 2017

Sub-Clause 20.2 of the 2017 Red, Yellow and Silver Books, for claims by either Party for time or money.

  1. 01

    Notice of Claim

    As soon as practicable, and no later than 28 days after the claiming Party became aware, or should have become aware, of the event (20.2.1).

  2. 02

    Engineer’s initial response

    If the Engineer considers the Notice late, it must say so within 14 days after receiving it, or the Notice is deemed valid (20.2.2).

  3. 03

    Fully detailed Claim

    Within 84 days after becoming aware: the event, the contractual or legal basis, the records relied on and the time or money claimed (20.2.4).

  4. 04

    Continuing effect

    The claim becomes interim, with updates at monthly intervals and a final claim within 28 days after the effects end (20.2.6).

  5. 05

    Agreement or determination

    The Engineer then agrees or determines the claim under Sub-Clause 3.7 (20.2.5).

1999 and 2017

What changed from the 1999 edition

The general conditions of the Red, Yellow and Silver Books. Your Particular Conditions may change any of these.

Rule2017 edition1999 edition
Claims clauseSub-Clause 20.2, for claims by either PartySub-Clause 20.1, for the Contractor’s claims
Notice of ClaimNo later than 28 days after becoming awareNo later than 28 days after becoming aware
If the notice is lateNo entitlement, but the Engineer must object within 14 days, and late notice can be found justifiedNo extension or payment, and the Employer is discharged
Fully detailed claim84 days after becoming aware42 days after becoming aware
If the legal basis is missingThe Notice of Claim lapses, unless the Engineer fails to say so within 14 daysAny failure is taken into account if it prejudiced the investigation of the claim
Continuing effectMonthly interim claims; final claim 28 days after the effects endMonthly interim claims; final claim 28 days after the effects end
Engineer’s answerAgreement or determination under Sub-Clause 3.7Approval or disapproval within 42 days after receiving the claim

Avoid the common mistakes

How claims are lost on notice

Relying on minutes or reports

Under the 2017 edition, a Notice must be identified as a Notice, so meeting minutes and progress reports don’t count unless they are.

Starting the clock too late

The 28 days run from when you became aware, or should have become aware, of the event, not from when its cost became clear.

Counting working days

FIDIC counts calendar days, so weekends and public holidays count. Send early if the last day falls when an office is closed.

Ignoring the Particular Conditions

Particular Conditions often change the periods, who receives Notices and how they are delivered. Enter your contract’s periods in the calculator.

Thin records

Keep contemporary records from the day the event starts. Both editions require them, and the Engineer may inspect them.

Assuming a late notice is fine

How strictly a time bar applies depends on the governing law and the facts. Take legal advice on any notice you think may be late.

Book a demo

Track every notice period on every project

Bunood computes contract deadlines with a rules engine set up from your contract, drafts cited responses to correspondence and assembles the evidence for claims. AI drafts, people decide.

  • A live demo, not slides
  • On your form of contract
  • Under NDA if you need one

4.9/5 average rating · 98% client satisfaction · 150+ clients served

Book a Bunood demo

We only use your details to reply to you. Arabic or English, as you prefer.

FAQ

FIDIC claims, answered

What is the FIDIC time bar?

Under Sub-Clause 20.1 of the 1999 edition and 20.2.1 of the 2017 edition, a claim for time or money must be notified no later than 28 days after the claiming Party became aware, or should have become aware, of the event. If it isn’t, the entitlement is lost and the other Party is discharged from liability.

How long do I have to submit a fully detailed claim?

42 days after becoming aware under the 1999 edition, and 84 days under the 2017 edition, unless the Engineer agrees another period. Particular Conditions may change both.

Are the 28 days calendar days or working days?

Calendar days. Weekends and public holidays count, and the day you became aware is day 0.

What should a Notice of Claim include?

A description of the event or circumstance, when you became aware of it and what you claim, sent to the Engineer as the Contract requires. Under the 2017 edition it must be identified as a Notice and refer to the Sub-Clause. The free template covers each point.

What if the event is still going on?

The fully detailed claim becomes interim. You send further interim claims at monthly intervals and a final claim within 28 days after the effects end.

Does the 2017 procedure apply to the Employer’s claims too?

Yes. Clause 20 of the 2017 edition applies the same procedure to claims by the Employer and the Contractor. In the 1999 edition, the Employer’s claims fall under Sub-Clause 2.5.

Does Bunood track FIDIC notice periods?

Yes. Bunood is configured for each project’s contract, FIDIC or bespoke, and a rules engine computes notice periods, such as the 28-day notice of claim, from the event date.

Is what I type stored?

No. The calculator runs in your browser, so nothing you type is sent to us or stored.